PJM-AH1-314
100 MW storage in Pittsylvania, VA · In queue since September 2021 · Proposed COD December 2025
100 MW
Capacity
1
Components
Battery
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH1-314 is a proposed 100 MW battery storage project located in Pittsylvania County, Virginia. The project is interconnected within the PJM Interconnection queue, with an entry date of September 11, 2021, and a proposed commercial operation date of December 31, 2025. The interconnecting utility is AEP.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the East Danville 138 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Pittsylvania
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
East Danville 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- EDANVILL69 KV T3
- POI Substation
- East Danville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.