PJM-AH1-316
4.4 MW generation in Dorchester, MD · In queue since September 2021 · Proposed COD December 2025
4.4 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH1-316 is a proposed solar generation project located in Dorchester County, Maryland, within the PJM Interconnection region. The project, with a total capacity of 4.4 MW, consists entirely of solar photovoltaic generation. Its point of interconnection is the Todd 25kV substation.
The project entered the PJM interconnection queue on September 11, 2021, with a proposed commercial operation date of December 31, 2025. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
MD
County
Dorchester
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Todd 25kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- TODD 25 KV DORCHSP1
- POI Substation
- Todd Substation