PJM-AH1-320
69 MW storage in Logan, OH · In queue since September 2021 · Proposed COD December 2025
69 MW
Capacity
1
Components
Battery
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH1-320 is a proposed battery storage project located in Logan County, Ohio. The project, with a total capacity of 69 MW, is interconnected to the Dayton utility via the Blue Jacket - Kirby 138 kV point of interconnection. It entered the PJM interconnection queue on September 10, 2021, with a proposed commercial operation date of December 31, 2025.
The interconnection agreement for PJM-AH1-320 is currently listed as "In Progress (unknown study)". The project consists solely of battery storage, with all 69 MW of capacity attributed to this technology.
Generated from interconnection queue and public data sources
State
OH
County
Logan
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
—
Point of Interconnection
Blue Jacket - Kirby 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-320