PJM-AH1-324
80 MW generation in Surry, VA · In queue since September 2021 · Proposed COD December 2025
80 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
4y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH1-324 is a proposed 80 MW solar generation project located in Surry County, Virginia. The project is in the PJM interconnection queue as of September 10, 2021, with a proposed commercial operation date of December 31, 2025. Dominion is the utility associated with the project.
The interconnection agreement for PJM-AH1-324 is currently listed as "In Progress (unknown study)". The point of interconnection is the Hopewell _x0013_ Surry 230 kV line.
Generated from interconnection queue and public data sources
State
VA
County
Surry
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Hopewell _x0013_ Surry 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SURRY4 22 KV G1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-324