PJM-AH1-328
21.3 MW hybrid in Logan, OH · In queue since September 2021 · Proposed COD December 2023
21.3 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
2y 3m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AH1-328 is a proposed 21.3 MW hybrid solar and battery project in Logan County, Ohio. The project, located within the PJM Interconnection region and to be served by Dayton utility, consists of 21.3 MW of solar capacity. It entered the PJM interconnection queue on September 10, 2021, with a proposed commercial operation date of December 31, 2023.
The interconnection agreement for PJM-AH1-328 is currently listed as "In Progress (unknown study)". The point of interconnection is the Blue Jacket - Kirby 138 kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OH
County
Logan
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
—
Point of Interconnection
Blue Jacket - Kirby 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.