Blue Jacket - Kirby 138 kV
206.55 MW generation in Logan, OH · In queue since February 2025
206.55 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Blue Jacket - Kirby 138 kV project is a proposed 206.55 MW solar generation project located in Logan County, Ohio. The project is in the PJM interconnection queue as entry PJM-AH1-328, which has been moved to TC2. The queue entry date is February 20, 2025.
The project's status is listed as active within the PJM queue. Dayton is the listed utility.
Generated from interconnection queue and public data sources
State
OH
County
Logan
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Blue Jacket - Kirby 138 kV