PJM-AH1-331
19.9 MW generation in Erie, PA · In queue since September 2021 · Proposed COD June 2023
19.9 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 9m
Schedule
36 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-01
PJM-AH1-331 is a proposed solar generation project located in Erie County, Pennsylvania, with a total capacity of 19.9 MW. The project, which interconnects to PENELEC via the Edinboro South-Erie South 25kV point of interconnection, entered the PJM interconnection queue on September 9, 2021. Its proposed commercial operation date is June 1, 2023.
The interconnection agreement for PJM-AH1-331 is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
PA
County
Erie
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Edinboro South-Erie South 25kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SOUTH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-331