Crystal Hill DP- Perth 115kV
69 MW generation in Halifax, VA · In queue since February 2025
69 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Crystal Hill DP- Perth 115kV project is a proposed 69 MW solar generation project located in Halifax County, Virginia. The development project is in the PJM interconnection queue as queue ID PJM-AH1-343, though it has been moved to TC2. The project entered the queue on February 4, 2025, as a Generation Interconnection request.
Dominion is the utility associated with the project. The project's status is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
VA
County
Halifax
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.