PJM-AH1-345
14 MW generation in Fauquier, VA · In queue since September 2021 · Proposed COD March 2023
14 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 6m
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-03-31
PJM-AH1-345 is a proposed solar generation project with a total capacity of 14 MW, located in Fauquier County, Virginia. The project is being developed within the Dominion service area and is interconnected to the PJM grid at the Remington 324 34.5 kV point of interconnection.
The project entered the PJM interconnection queue on September 10, 2021, with a proposed commercial operation date of March 31, 2023. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
Fauquier
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Remington 324 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.