PJM-AH1-354
40 MW storage in Stephenson, IL · In queue since September 2021 · Proposed COD September 2024
40 MW
Capacity
1
Components
Battery
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3 years
Schedule
20 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-10
PJM-AH1-354 is a proposed 40 MW battery storage project located in Stephenson County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 10, 2021, with a proposed commercial operation date of September 10, 2024. The interconnecting utility is ComEd, and the point of interconnection is Lena 138 kV.
The interconnection agreement status for the project is listed as "In Progress (unknown study)". The developer is not specified in the queue data. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
IL
County
Stephenson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Lena 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-354