PJM-AH1-376
28 MW generation in Greenbrier, WV · In queue since September 2021 · Proposed COD June 2025
28 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
PJM-AH1-376 is a proposed solar generation project located in Greenbrier County, West Virginia. The project, with a total capacity of 28 MW, is in the PJM interconnection queue as of September 10, 2021. The proposed commercial operation date is June 1, 2025.
The interconnection agreement for PJM-AH1-376 with utility APS is currently in progress, with the specific study type unknown. The point of interconnection is the Ronceverte - Clenden 46 kV line. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
WV
County
Greenbrier
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Ronceverte - Clenden 46 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.