PJM-AH1-387
150 MW generation in Hampshire, WV · In queue since September 2021 · Proposed COD January 2025
150 MW
Capacity
1
Components
Wind
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 4m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-01-09
PJM-AH1-387 is a proposed wind generation project with a total capacity of 150 MW. The project is located in Hampshire County, West Virginia, and is interconnected within the PJM Interconnection region. The queue entry date for the project is September 10, 2021, with a proposed commercial operation date of January 9, 2025.
The interconnection agreement for PJM-AH1-387 is currently listed as "In Progress (unknown study)". The project's point of interconnection (POI) is the Meadowbrook-Mount Storm 500kV line, and the interconnecting utility is APS.
Generated from interconnection queue and public data sources
State
WV
County
Hampshire
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Meadowbrook-Mount Storm 500kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.