PJM-AH1-390
19.9 MW generation in Northumberland, PA · In queue since September 2021 · Proposed COD July 2023
19.9 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 10m
Schedule
34 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-07-31
PJM-AH1-390 is a proposed solar generation project with a total capacity of 19.9 MW, located in Northumberland County, Pennsylvania. The project is in the PJM interconnection queue as of September 10, 2021, with a proposed commercial operation date of July 31, 2023. The interconnection agreement status is listed as "In Progress (unknown study)". The interconnecting utility is PPL.
The development project consists of 19.9 MW of solar photovoltaic generation. It is currently listed as an active project within the PJM queue. The point of interconnection is TBD at 69 kV.
Generated from interconnection queue and public data sources
State
PA
County
Northumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
TBD 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-390