PJM-AH1-392
90 MW generation in St. Joseph, IN · In queue since September 2021 · Proposed COD July 2025
90 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 10m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-07-16
PJM-AH1-392 is a proposed 90 MW solar generation project located in St. Joseph County, Indiana. The project, which consists of 90 MW of solar photovoltaic generation, is in the PJM interconnection queue as of September 10, 2021. The proposed commercial operation date is July 16, 2025. The interconnecting utility is AEP.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Gravel Pit 138 kV substation.
Generated from interconnection queue and public data sources
State
IN
County
St. Joseph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Gravel Pit 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.