Gary 24.94 kV
11.891 MW generation in Lunenburg, VA · In queue since February 2025
11.891 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Gary 24.94 kV project is a proposed solar generation project with a total capacity of 11.89 MW, located in Lunenburg County, Virginia. The project is being developed within the Dominion service area and has appeared in recent news coverage.
The project is listed in the PJM interconnection queue as PJM-AH1-396, having been moved to TC2. It entered the queue on February 21, 2025, as a Generation Interconnection project. The project's status is currently listed as active.
Generated from interconnection queue and public data sources
State
VA
County
Lunenburg
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Gary 24.94 kV