PJM-AH1-429
90 MW generation in Fleming, KY · In queue since September 2021 · Proposed COD September 2026
90 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
5 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
PJM-AH1-429 is a proposed 90 MW solar generation project located in Fleming County, Kentucky. The project is in the PJM interconnection queue, having entered on September 10, 2021, with a proposed commercial operation date of September 1, 2026. The interconnecting utility is EKPC.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Flemingsburg - Spurlock 138 kV line.
Generated from interconnection queue and public data sources
State
KY
County
Fleming
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Flemingsburg - Spurlock 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-429