PJM-AH1-440
34 MW storage in Cumberland, VA · In queue since September 2021 · Proposed COD September 2026
34 MW
Capacity
1
Components
Battery
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
5 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-01
PJM-AH1-440 is a proposed 34 MW battery storage project located in Cumberland County, Virginia. The project is being developed within the Dominion service area and is interconnected to the PJM Interconnection queue. Its queue entry date is September 10, 2021, with a proposed commercial operation date of September 1, 2026.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Buckingham- Farmville 230kV line.
Generated from interconnection queue and public data sources
State
VA
County
Cumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Buckingham- Farmville 230kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-440