PJM-AH1-447
60 MW hybrid in Pittsylvania, VA · In queue since September 2021 · Proposed COD December 2024
60 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-02
PJM-AH1-447 is a proposed 60 MW hybrid solar and battery project located in Pittsylvania County, Virginia. The project, which interconnects to the AEP utility via the Axton _x0013_ Danville #2 138 kV point of interconnection, entered the PJM interconnection queue on September 10, 2021. Its proposed commercial operation date is December 2, 2024.
The interconnection agreement for PJM-AH1-447 is currently listed as "In Progress (unknown study)". The project consists of 60 MW of solar generation capacity, and also includes battery storage.
Generated from interconnection queue and public data sources
State
VA
County
Pittsylvania
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Axton _x0013_ Danville #2 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- AXTONAEP34.5 KV AXTONSP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-447