Buckhorn 138 kV
80 MW storage in Tazewell, VA · In queue since February 2025
80 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Buckhorn 138 kV project is a proposed 80 MW battery storage development in Tazewell County, Virginia. The project is located within the PJM Interconnection region and is being managed by AEP.
The project, identified as PJM-AH1-461 (later moved to TC2) in the PJM queue, entered the queue on February 20, 2025. The service type is Generation Interconnection, and the project is currently listed as active.
Generated from interconnection queue and public data sources
State
VA
County
Tazewell
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Buckhorn 138 kV