PJM-AH1-463
80 MW generation in Bath, KY · In queue since September 2021 · Proposed COD December 2024
80 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AH1-463 is a proposed solar generation project with a total capacity of 80 MW, located in Bath County, Kentucky. The project is being developed within the PJM Interconnection queue, with a queue entry date of September 10, 2021. The proposed commercial operation date is December 31, 2024.
The interconnection agreement for PJM-AH1-463 is currently listed as "In Progress (unknown study)". The designated point of interconnection (POI) is the Owingsville - Preston 69 kV line. The interconnecting utility is East Kentucky Power Cooperative (EKPC).
Generated from interconnection queue and public data sources
State
KY
County
Bath
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Owingsville - Preston 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.