Waterford Solar 1
20 MW generation in Erie, PA · In queue since September 2021 · Proposed COD July 2024
20 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 10m
Schedule
21 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-07-30
Waterford Solar 1 is a proposed 20 MW solar generation project located in Erie County, Pennsylvania. The project is in the PJM interconnection queue as entry AH1-491, with a queue entry date of September 11, 2021, and a proposed commercial operation date of July 30, 2024. The project's interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project is located within the PENELEC utility service area and interconnects to the Union City 34.5 kV point of interconnection. The developer is not specified in the available data. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
PA
County
Erie
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Union City 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Waterford Solar 1