PJM-AH1-528
300.8 MW generation in Brunswick, VA · In queue since September 2021 · Proposed COD March 2025
300.8 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 6m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-30
PJM-AH1-528 is a proposed solar generation project located in Brunswick County, Virginia, within the PJM Interconnection region. The project, with a total capacity of 300.8 MW, is being developed within Dominion's service territory. The project consists of 300.8 MW of solar photovoltaic generation.
The project entered the PJM interconnection queue on September 10, 2021, and has a proposed commercial operation date of March 30, 2025. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Rawlings 500kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Brunswick
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Rawlings 500kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- RAWLINGS500 KV 1BUCK
- POI Substation
- Rawlings Substation