PJM-AH1-533
96.2 MW hybrid in Perry, PA · In queue since September 2021 · Proposed COD March 2025
96.2 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 6m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-01
PJM-AH1-533 is a proposed 96.2 MW hybrid solar and battery project located in Perry County, Pennsylvania. The project, which interconnects with PPL, entered the PJM interconnection queue on September 10, 2021, with a proposed commercial operation date of March 1, 2025.
The interconnection agreement status is currently listed as "In Progress (unknown study)". The development project consists of 96.2 MW of solar generation capacity. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
PA
County
Perry
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Sunbury-Juniata II
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-533