PJM-AH1-535
133.6 MW generation in Hawkins, TN · In queue since September 2021 · Proposed COD March 2025
133.6 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 6m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-01
PJM-AH1-535 is a proposed solar generation project with a total capacity of 133.6 MW. The project is located in Hawkins County, Tennessee, and is interconnected within the PJM Interconnection queue. The queue entry date is September 10, 2021, with a proposed commercial operation date of March 1, 2025. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project is being developed within the American Electric Power (AEP) service territory. The point of interconnection is the Nagel - Cane River 230 kV line. This proposed project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
State
TN
County
Hawkins
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Nagel - Cane River 230 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 955 RIVE16 KV RV-2