Nagel - Cane River 230 kV
100 MW generation in Hawkins, TN · In queue since March 2025
100 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Nagel - Cane River 230 kV project is a proposed 100 MW solar and battery storage generation project located in Hawkins County, Tennessee. The project consists of both solar and storage components, but individual capacities are not specified. It is listed in the PJM interconnection queue as queue ID PJM-AH1-535, which was moved to TC2.
The project's queue entry date is March 6, 2025. The developer is not specified in the available data. The project is currently listed as active in the queue. No information is available regarding a proposed commercial operation date, interconnection agreement status, or links to existing operating plants. There is no indication of recent news coverage.
Generated from interconnection queue and public data sources
State
TN
County
Hawkins
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.