PJM-AH1-538
241.5 MW hybrid in Van Wert, OH · In queue since September 2021 · Proposed COD March 2025
241.5 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 6m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-01
PJM-AH1-538 is a proposed 241.5 MW hybrid solar and battery project located in Van Wert County, Ohio. The project, which consists of 241.5 MW of solar capacity, is interconnected within the PJM Interconnection queue. The queue entry date is September 10, 2021, with a proposed commercial operation date of March 1, 2025. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed project is located within the AEP utility territory and its point of interconnection is the East Lima - Haviland 138 kV line. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
OH
County
Van Wert
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
East Lima - Haviland 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-538