PJM-AH1-545
200 MW hybrid in Washington, PA · In queue since September 2021 · Proposed COD March 2025
200 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 6m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-01
The proposed project PJM-AH1-545 is a 200 MW solar and battery hybrid development in Washington County, Pennsylvania. The project consists of 200 MW of solar generation, paired with an unspecified amount of battery storage. It is located within the PJM Interconnection region and is being managed by APS.
The project entered the PJM interconnection queue on September 10, 2021, with a proposed commercial operation date of March 1, 2025. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is at the Wylie Ridge-Tidd 345kV substation.
Generated from interconnection queue and public data sources
State
PA
County
Washington
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Wylie Ridge-Tidd 345kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-545