Chalk Point 230 kV
670.2 MW generation in Prince George's, MD · In queue since March 2025
670.2 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Chalk Point 230 kV project is a proposed 670.2 MW solar and battery energy storage development in Prince George's County, Maryland. The project consists of both solar and storage components, and is located within the PEPCO service area.
The project is listed in the PJM interconnection queue as entry PJM-AH1-552, which was subsequently moved to queue TC2. The queue entry date is March 4, 2025. The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
MD
County
Prince George's
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PEPCO
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.