Project PJM-AH1-558 — Project Summary

Queue ID
PJM-AH1-558
Capacity
250 MW
Technology
Battery
Status
active
Location
Hanover, VA
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AH1-558

PJM-AH1-558BetaActiveBatteryPJMLBNL

250 MW storage in Hanover, VA · In queue since September 2021 · Proposed COD June 2025

250 MW

Capacity

1

Components

Battery

4y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection

Total Duration

3y 9m

Schedule

11 months past proposed COD

In Study38%
Queue EntrySep 10, 2021

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-01

About

PJM-AH1-558 is a proposed 250 MW battery storage project located in Hanover County, Virginia. The project, under development within the Dominion service area, consists of a 250 MW battery component. It is listed in the PJM interconnection queue as of September 10, 2021, with a proposed commercial operation date of June 1, 2025.

The interconnection request, designated PJM-AH1-558, is currently listed as "In Progress (unknown study)" for its Interconnection Agreement (IA) status. The point of interconnection (POI) is the Four Rivers 230kV substation.

Generated from interconnection queue and public data sources

Project Details

State

VA

County

Hanover

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

Dominion

Entity

PJM

Service Type

Point of Interconnection

Four Rivers 230kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
DOMINION HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
FOURRIVR13.8 KV GT501
POI Substation
Four Rivers Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AH1-558