PJM-AH1-565
250 MW storage in Wood, OH · In queue since September 2021 · Proposed COD June 2025
250 MW
Capacity
1
Components
Battery
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
PJM-AH1-565 is a proposed 250 MW battery storage project located in Wood County, Ohio. The project, which consists entirely of battery storage, is interconnected with American Transmission Systems, Inc. (ATSI). It entered the PJM interconnection queue on September 10, 2021, with a proposed commercial operation date of June 1, 2025.
The project's interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
OH
County
Wood
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Lemoyne 345kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LEMOYNE218 KV UN1
- POI Substation
- Lemoyne Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-565