PJM-AH1-569
49.99 MW generation in Union, OH · In queue since September 2021 · Proposed COD December 2024
49.99 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
PJM-AH1-569 is a proposed solar generation project with a total capacity of 49.99 MW. The project is located in Union County, Ohio, within the PJM Interconnection region and is being managed by utility ATSI. The project entered the PJM queue on September 10, 2021, with a proposed commercial operation date of December 1, 2024.
The interconnection status for PJM-AH1-569 is listed as "In Progress (unknown study)". The point of interconnection is the Broadview - Tangy 138 kV III substation.
Generated from interconnection queue and public data sources
State
OH
County
Union
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Broadview - Tangy 138 kV III
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.