PJM-AH1-570
25 MW generation in KY · In queue since September 2021 · Proposed COD December 2024
25 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
PJM-AH1-570 is a proposed solar generation project located in Kentucky, within the PJM Interconnection region. The project, with a total capacity of 25 MW, consists entirely of solar photovoltaic generation. Its point of interconnection is the Millersburg 69 kV substation.
The project entered the PJM interconnection queue on September 10, 2021, and has a proposed commercial operation date of December 1, 2024. The interconnection agreement is currently listed as "In Progress (unknown study)". The interconnecting utility is EKPC.
Generated from interconnection queue and public data sources
State
KY
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Millersburg 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WMILBURG69 KV LOAD1
- POI Substation
- West Millersburg Substation