PJM-AH1-571
20 MW generation in KY · In queue since September 2021 · Proposed COD December 2024
20 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
PJM-AH1-571 is a proposed 20 MW solar generation project located in Kentucky. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 10, 2021, with a proposed commercial operation date of December 1, 2024. The interconnecting utility is EKPC, and the point of interconnection is the Millersburg 69 kV substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
KY
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Millersburg 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WMILBURG69 KV LOAD1
- POI Substation
- West Millersburg Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-571