PJM-AH1-572
30 MW generation in Marion, OH · In queue since September 2021 · Proposed COD December 2024
30 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-01
PJM-AH1-572 is a proposed 30 MW solar generation project located in Marion County, Ohio. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 10, 2021. The proposed commercial operation date is December 1, 2024. The project's interconnection agreement status is currently listed as "In Progress (unknown study)". The interconnecting utility is AEP, and the point of interconnection is the South Morral 69 kV substation.
The development project consists of 30 MW of solar photovoltaic generation. It is currently listed as an active project within the PJM queue.
Generated from interconnection queue and public data sources
State
OH
County
Marion
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
South Morral 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SOUTH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-572