PJM-AH1-577
70 MW generation in Wayne, OH · In queue since September 2021 · Proposed COD October 2028
70 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-15
PJM-AH1-577 is a proposed 70 MW solar generation project located in Wayne County, Ohio. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 10, 2021. The proposed commercial operation date is October 15, 2028. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project, which is being developed within the AEP utility territory, consists of 70 MW of solar photovoltaic generation. The point of interconnection is at the Tigers 69 kV substation. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
OH
County
Wayne
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Tigers 69 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Tiger
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-577