PJM-AH1-590
50 MW generation in Grant, WV · In queue since September 2021 · Proposed COD December 2024
50 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-16
PJM-AH1-590 is a proposed 50 MW solar generation project located in Grant County, West Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 10, 2021, with a proposed commercial operation date of December 16, 2024. The designated point of interconnection is the Cherry Ridge 66 kV substation.
The interconnection agreement for PJM-AH1-590 is currently listed as "In Progress (unknown study)". The project is being developed within the service territory of utility APS.
Generated from interconnection queue and public data sources
State
WV
County
Grant
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Cherry Ridge 66 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-590