PJM-AH1-617
200 MW generation in KY · In queue since September 2021 · Proposed COD September 2024
200 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3 years
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-30
PJM-AH1-617 is a proposed solar generation project located in Kentucky with a total capacity of 200 MW. The project is listed in the PJM interconnection queue as of September 10, 2021, with a proposed commercial operation date of September 30, 2024. The interconnecting utility is AEP.
The interconnection agreement status for PJM-AH1-617 is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
KY
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Beaver Creek 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BEAVERCR46 KV WHEELWRT
- POI Substation
- Bever Creek
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-617