Harbert Metering 138 kV
200 MW generation in KY · In queue since February 2025
200 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Harbert Metering 138 kV project is a proposed 200 MW solar generation project located in Kentucky within the PJM Interconnection region. The project, sponsored by AEP, entered the PJM queue as AH1-617 on February 21, 2025, and has since been moved to queue TC2.
The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
KY
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.