PJM-AH1-637
16 MW generation in Westmoreland, VA · In queue since September 2021 · Proposed COD December 2022
16 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
1y 3m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-15
PJM-AH1-637 is a proposed 16 MW solar generation project located in Westmoreland County, Virginia. The project is interconnected within the PJM Interconnection queue under Dominion, with a queue entry date of September 13, 2021. The proposed commercial operation date is December 15, 2022.
The interconnection agreement (IA) status for PJM-AH1-637 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Oak Grove 34.5 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Westmoreland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Oak Grove 34.5 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-637