PJM-AH1-644
100 MW generation in KY · In queue since September 2021 · Proposed COD January 2026
100 MW
Capacity
1
Components
Solar
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 4m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-01
PJM-AH1-644 is a proposed 100 MW solar generation project located in Kentucky within the PJM Interconnection region. The project, with American Electric Power (AEP) as the utility, entered the PJM queue on September 15, 2021, and has a proposed commercial operation date of January 1, 2026.
The interconnection agreement (IA) for the project is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Spicewood 138 kV substation.
Generated from interconnection queue and public data sources
State
KY
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Spicewood 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Spicewood
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-644