PJM-AH1-661
15.32 MW generation in Muskingum, OH · In queue since September 2021 · Proposed COD July 2023
15.32 MW
Capacity
1
Components
Other
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 10m
Schedule
35 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-07-01
The proposed project PJM-AH1-661 is a 15.32 MW generation project of unspecified technology located in Muskingum County, Ohio. The project is interconnected within the PJM Interconnection queue, with an original queue entry date of September 29, 2021. The proposed commercial operation date is July 1, 2023.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The interconnecting utility is AEP. The point of interconnection (POI) is the Philo _x0013_ Cannelville Switch 138 kV.
Generated from interconnection queue and public data sources
State
OH
County
Muskingum
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Philo _x0013_ Cannelville Switch 138 kV
Data Source
LBNL
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH1-661