Cannelville 12.47 kV
10.07 MW generation in Muskingum, OH · In queue since February 2025
10.07 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Cannelville 12.47 kV project is a proposed 10.07 MW generation project located in Muskingum County, Ohio. The project, utilizing an unspecified "Other" technology, is being developed within the American Electric Power (AEP) service area.
The project is listed in the PJM interconnection queue as entry PJM-AH1-661, which was subsequently moved to TC2. The queue entry date is February 18, 2025. The project's current status is listed as active.
Generated from interconnection queue and public data sources
State
OH
County
Muskingum
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.