Valero 69 kV
61 MW generation in Gloucester, NJ · In queue since April 2025
61 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Total Duration
1y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Valero 69 kV project is a proposed 61 MW gas-fired generation project located in Gloucester County, New Jersey. The project is listed in the PJM interconnection queue as entry PJM-AH1-701, which was moved to TC2. The queue entry date is April 11, 2025.
The project's listed fuel sources are natural gas and oil. The interconnection service type is Generation Interconnection. The project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
NJ
County
Gloucester
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Valero 69 kV