Bergen 230kV
670.61 MW generation in Bergen, NJ · In queue since April 2025
670.61 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Total Duration
1y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Bergen 230kV project is a proposed 670.61 MW natural gas generation project located in Bergen County, New Jersey. The project is being developed within the PJM Interconnection queue as project "PJM-AH1-703 - moved to TC2" and is listed as active. The queue entry date is April 8, 2025.
The project is a Generation Interconnection project within the PJM service area. The interconnecting utility is PSEG.
Generated from interconnection queue and public data sources
State
NJ
County
Bergen
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PSEG
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.