Lordstown 345 kV
970.453 MW generation in Trumbull, OH · In queue since April 2025
970.453 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Total Duration
1y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Lordstown 345 kV project is a proposed 970.45 MW natural gas generation project located in Trumbull County, Ohio. The project is in the PJM interconnection queue as entry PJM-AH1-706, which has been moved to TC2. The queue entry date is April 7, 2025.
The project is listed as active in the queue. The interconnecting utility is ATSI, and the service type is Generation Interconnection.
Generated from interconnection queue and public data sources
State
OH
County
Trumbull
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Lordstown 345 kV