Salem 500kV (PJM-AH1-710 - moved to TC2) — Project Summary

Queue ID
PJM-AH1-710 - moved to TC2
Capacity
2650.8 MW
Technology
Nuclear
Status
active
Location
Salem, NJ
Region
PJM
Developer
IA Status

Salem 500kV

PJM-AH1-710 - moved to TC2BetaActiveNuclearPJMLive · PJM

2,650.8 MW generation in Salem, NJ · In queue since April 2025

2,650.8 MW

Capacity

0

Components

1y 1m

In Queue

IA Status

Interconnection

Total Duration

1y 1m

Pre-Study0%
Queue EntryApr 9, 2025

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

The Salem 500kV project is a proposed 2650.8 MW nuclear generation project located in Salem County, New Jersey. Developed by PSEG, the project is listed in the PJM interconnection queue as entry PJM-AH1-710, which has been moved to TC2. The queue entry date is April 9, 2025.

The project is currently listed as active in the interconnection queue. Recent news coverage indicates industry interest in the development.

Generated from interconnection queue and public data sources

Project Details

State

NJ

County

Salem

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

PSEG

Entity

PJM

Service Type

Generation Interconnection

Data Source

Live · PJM

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Salem 500kV