Mt. Storm 500kV (PJM-AH1-713 - moved to TC2) — Project Summary

Queue ID
PJM-AH1-713 - moved to TC2
Capacity
538 MW
Technology
Coal
Status
active
Location
Grant, WV
Region
PJM
Developer
IA Status

Mt. Storm 500kV

PJM-AH1-713 - moved to TC2BetaActiveCoalPJMLive · PJM

538 MW generation in Grant, WV · In queue since April 2025

538 MW

Capacity

0

Components

1y 1m

In Queue

IA Status

Interconnection

Total Duration

1y 1m

Pre-Study0%
Queue EntryApr 7, 2025

Interconnection request submitted to ISO/RTO

System Impact Study

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

The Mt. Storm 500kV project is a proposed 538 MW coal-fired generation project located in Grant County, West Virginia. The project is being developed within the Dominion service area and has appeared in recent news coverage.

The project is listed in the PJM interconnection queue as entry PJM-AH1-713, which has been moved to TC2. The queue entry date is April 7, 2025. The project's status is currently listed as active.

Generated from interconnection queue and public data sources

Project Details

State

WV

County

Grant

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

Dominion

Entity

PJM

Service Type

Generation Interconnection

Data Source

Live · PJM

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Mt. Storm 500kV