Linden 230kV
806.4 MW generation in Union, NJ · In queue since April 2025
806.4 MW
Capacity
0
Components
1y 1m
In Queue
—
IA Status
Total Duration
1y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Linden 230kV project is a proposed 806.4 MW natural gas generation project located in Union County, New Jersey. The project is being developed within the PJM Interconnection queue under queue ID PJM-AH1-722, which was moved to TC2. The queue entry date is April 8, 2025.
The project is listed as active in the interconnection queue. The interconnecting utility is PSEG.
Generated from interconnection queue and public data sources
State
NJ
County
Union
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PSEG
Entity
PJM
Service Type
Generation Interconnection
Data Source
Live · PJM
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Linden 230kV