PJM-AH2-002
80 MW generation in Barren, KY · In queue since October 2021 · Proposed COD December 2024
80 MW
Capacity
1
Components
Solar
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AH2-002 is a proposed solar generation project with a total capacity of 80 MW, located in Barren County, Kentucky. The project is being developed within the PJM Interconnection queue, with queue entry dated October 2, 2021. The proposed commercial operation date is December 31, 2024.
The interconnection agreement for PJM-AH2-002 is currently listed as "In Progress (unknown study)". The project is interconnected to East Kentucky Power Cooperative (EKPC) at the Temple Hill - Roseville 69 kV point of interconnection. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
KY
County
Barren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Temple Hill - Roseville 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-002