PJM-AH2-009
40 MW generation in Morrow, OH · In queue since October 2021 · Proposed COD December 2024
40 MW
Capacity
1
Components
Solar
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 2m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AH2-009 is a proposed solar generation project located in Morrow County, Ohio, within the PJM Interconnection region. The project, with a total capacity of 40 MW, consists entirely of solar photovoltaic technology. Its interconnection queue entry date is October 8, 2021, with a proposed commercial operation date of December 31, 2024. The interconnecting utility is ATSI.
The project's interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
OH
County
Morrow
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Galion 138 kV V
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- GALION 34.5 KV BLOSSOSP
- POI Substation
- Galion Substation